Educational Facility Upgrade

Scope Of Work

Responsiveness Gets a 4.0!

BGSU Summer Slam 2015 called for intensive timing and simultaneous renovations of four key campus buildings:
Olscamp Hall

  • Complete make-over included new ceilings, flooring, paint, lighting and upgraded technology

Education Building

  • New face-lift on the 2nd floor included new flooring, painting and ceilings to 5 classrooms, renovated hallway and upstairs restrooms

Eppler, Math/Science Building

  • Fresh paint and new flooring in 41 classrooms

Business Administration Building

  • Fresh paint and new flooring

Lakeside performed all renovations around BGSU’s summer class schedule and took only 10 weeks to complete all four.